Schedule 1 - Works and Services Requirements
Utility Requirements

Abbreviation

Requirement

WTR Community water system. In subdivisions which are to be provided with a community water system, each Parcel within the proposed subdivision, or Parcel being Developed, must be supplied by a water distribution system, including service connections, and with adequate fire flow and protection, which is designed in accordance with the standards prescribed in the Design Standards Water Section.
WELL Where a community water system is not available a proven water supply located on each parcel is permitted.
SWR Community sanitary sewer system.
SWRSEP Sanitary sewer collection and disposal or Sanitary sewage effluent ground disposal in accordance with Part 2, Section 5.2 (o)(viii) of this bylaw.
DITCH Drainage collection and disposal system by open ditches and culverts.
STM Closed drainage collection and disposal system (i.e., a system other than open ditches). 
SL Street lighting throughout the subdivision.
SLI Street lighting at street intersections only.
OH Overhead electrical and communication wiring. 
UG Underground electrical and communication wiring.
W Communication and electrical wiring to conform to the highest standard of existing adjacent facilities

 

Utilities

(Refer to the Key Sheet Above)
Zone1 Water Sewer Drain Wiring Lighting
A1 WELL SWRSEP DITCH OH SLI
A2 WELL SWRSEP DITCH OH SLI
RR1 WTR SWRSEP DITCH OH SLI
RR2 WTR SWR DITCH OH SLI
RU1 WTR SWR STM UG SL
RU2 WTR SWR STM UG SL
RU3 WTR SWR STM UG SL
RU4 WTR SWR STM UG SL
RU5 WTR SWR STM UG SL
MF1 WTR SWR STM UG SL
MF2 WTR SWR STM UG SL
MF3 WTR SWR STM UG SL
MH1 WTR SWR STM UG SL
HD1 WTR SWR STM UG SL
HD2 WTR SWR STM UG SL
C1 WTR SWR STM UG SL
C2 WTR SWR STM UG SL
VC1 WTR SWR STM UG SL
UC1-5 WTR SWR STM UG SL
CA1 WTR SWR STM UG SL
I1 WTR SWR STM UG SL
I2 WTR SWR STM UG SL
I3 WTR SWRSEP DITCH OH SLI
I4 WELL SWRSEP DITCH OH SLI
P1 WTR SWR STM UG SL
P2 WTR SWR STM UG SL
P3 WELL SWRSEP STM W SLI
P4 WELL SWRSEP STM W SL
W1 N/A N/A N/A N/A N/A
W2 As Required Based on Development Proposal
CD(3) WTR SWR STM UG SL
CD12 WTR SWR STM UG SL

Notes:

  1. Comprehensive Development Zones listed in Section 17 of the Zoning Bylaw, except the CD12 – Airport zone.
  2. The zones identified in this table are the zones designated in the Zoning Bylaw. Properties with an 's'. ‘b’. ‘h’, ‘lp’ or ‘rls’ as part of the zoning designation shall comply with the works and services requirements of the parent zone (e.g. RU1s shall comply with the requirements of the RU1 zone.)
Road Requirements

Road requirements (refer to Standard Drawings) are determined using Table 2 below and Section 4.2 – Road Classifications.

  1. Roadway classifications identified within the Map 13.1 - Functional Road Classification of the City’s Official Community Plan (OCP).
  2. OCP Functional Road Classification Overlays:
  3. Consideration of the local context; the local context may include considerations such as, but not limited to:
    • Fixed elements unlikely to change over time, like topography, water bodies, environmentally sensitive areas, agricultural land reserves, First Nations reserves, etc.
    • Atypical frontages, for example schools, recreational facilities, parks, industrial loading areas, etc.
  4. This Bylaw prescribes infrastructure design and practices. Council recognizes that each situation is unique, and solutions may need to be tailored to the existing conditions. As such, discretion is afforded the City Engineer to ensure the optimal technical solutions are implemented and adapt the prescribed practices herein to suit the individual project/site requirements.
Roadway Classification OCP Map 13.1 OCP Map 13.3 - Biking Overlay Notes:
Not on Biking Overlay On Secondary Biking On Primary Biking Route
Laneway Hillside XS-Ro1 Consult with City Engineer  
Suburban XS-Ro2  
Core Area XS-Ro2  
Urban Centre XS-Ro2  
Local Rural XS-R20 Consult with City Engineer  
Hillside XS-R21 Village Local-Residential, development fronts at least one side
Hillside XS-R22 Condition A, development fronts both sides
Hillside XS-R23 Condition B, development fronts one side only
Hillside XS-R24 Condition C, no development fronts street
Suburban XS-R25  
Industrial XS-R26  
Core Area XS-R27  
Urban Centre XS-R28  
Collector Rural XS-R40 Consult with City Engineer  
Hillside XS-R41 Consult with City Engineer Village Collector Condition A, where commercial development fronts street
Hillside XS-R42 Village Collector Condition B, where no commercial development fronts street
Hillside XS-R43 Collector Condition A, development fronts both sides
Hillside XS-R44 Collector Condition B, development fronts one side only
Hillside XS-R45 Collector Condition C, no development fronts street
Hillside XS-R46 Minor Collector Condition A, development fronts both sides or, 
development fronts one side only
Hillside XS-R47 Minor Collector Condition B, no development fronts street
Suburban XS-R48 XS-R49  
Industrial XS-R50 Consult with City Engineer  
Core Area XS-R51 XS-R52  

Urban Centre

XS-R53 XS-R54  
Minor Arterial Rural XS-R60 XS-R61  
Hillside XS-R62 Consult with City Engineer Consult with City Engineer Arterial Condition A, within village centre where environmental conditions 
permit
Hillside XS-R63 Arterial Condition B, within 10-minute walking distance of village centre; or, 
within village centre where environmental conditions do not permit the use 
of Condition A
Hillside XS-R64 Arterial Condition C, greater than a 10-minute walking distance from 
village centre.
Suburban XS-R65  
Core Area XS-R66  
Urban Centre XS-R67  
Major Arterial

Rural 3-Lane

XS-R80 XS-R81  
Rural 5-Lane XS-R82 XS-R83  
Suburban 3-Lane XS-R84 Consult with City Engineer  
Suburban 5-Lane XS-R85  
Core Area 3-Lane XS-R86  
Core Area 5-Lane XS-R87  
Urban Centre 3-Lane XS-R88  
Urban Centre 5-Lane XS-R89  

Notes:

  1. Active Transportation Corridors not located with road right-of-way’s such as but not limited to the Okanagan Rail Trail and Mission Creek Greenway, are transportation corridors requiring frontage improvements.
  2. Pedestrian facilities are required on any road fronting a school or major recreational facility in rural land use areas.
  3. Where a primary Biking Route is identified on OCP Map 13.3 Bike Overlay Map up to 2 m of additional ROW may be required.
  4. Where a Rapid Transit or Frequent Transit Network is identified on OCP Map 13.2 –Transit Overlay up to 3 m of additional ROW may be required on Local, Collector, and Minor Arterial roads and up to 6 m of additional ROW may be required on Major Arterial roads.
  5. Where OCP Maps 13.2, 13.3, 13.4, and 13.5 overlays are present, consult with City Engineer for design requirements.

 

Linear Park Trails Requirements

Linear Park requirements (refer to Standard Drawings) are determined using Table 3: Trail Requirements, Map 10.1 - Linear Corridors of the City’s Official Community Plan (OCP).

Class Dimensions Longitudinal Slope Cross Slope Materials
Trail Class Trail Type (W) Width (C) Clear Zone (H) Min. Vertical Clearance (S) Typical Slope (S) Slope for Short Sections (max. 10m) Cross Slope Surface Type (M1) Type Depth (M2) Granular Base

(M3) Sub-Base

(M4) Compacted Sub-Grade
1 Major Urban Promenade 4.5m or greater 0.5m 3.0m 5% max. (1:20) 8% max. (1:12) 2% min. Asphalt 50mm 100mm 200mm 95% MPD
Concrete or Brick 100mm or 75mm 100mm N/A 95% MPD
2 Major Multi-Use (Urban) 4.5 - 3.0m 0.5m 3.0m 8% max. (1:12) 12% max. (1:8) 2% min. Asphalt 50mm 100mm 200mm 95% MPD
Concrete or Brick 60mm 100mm N/A 95% MPD
3 Major Multi-Use (Rural) 4.5 - 3.0m 0.5m 2.5m 8% max. (1:12) 12% max. (1:8) 2% min. Asphalt 50mm 75mm 150mm 95% MPD
Concrete or Brick 60mm 100mm N/A 95% MPD
4 Standard Multi-Use 3.0 - 2.0m 0.5m 3.0 - 2.5m 8% max. (1:12) 15% max. (1:7) 2% min. Asphalt millings 60mm 75mm 150mm 95% MPD
Aggregate 50mm 100mm N/A 95% MPD
5 Narrow Multi-Use 1.5 - 1.2m 0.5m 2.5m 8% max. (1:12) 15% max. (1:7) 2% min. Asphalt millings 60mm 75mm 150mm 95% MPD
Aggregate 50mm 100mm N/A 95% MPD
6 Nature Trails 1.2 - 0.6m 0.5m 2.5m 20% (1:5) max. hiking & walking Over 20% use steps, etc. 2% min. Natural ground N/A N/A N/A 95% MPD
15% (1:7) max. mountain biking 15% Aggregate if needed 50mm 100mm N/A 95% MPD

Table 3 - Linear Parks Trail Requirements Standard Drawing